Stormwater Projects and Services

CAPITAL IMPROVEMENT PROJECTS

Click photos to view larger.

Chadbourne and Chelwood Culvert Replacements

Chadbourne

2 – 7’ x 6’ box culverts

Chelwood

2 – 7’ x 7’ box culverts

Currently under construction.  Construction estimated to be completed in early 2021.  

Glen Eagles Lane Culvert Replacement

2 - 7' x 6' box culverts

In easement acquisition and permitting.

 

 

 

 

COMPLETED PROJECTS

Havencrest Culvert Replacement

2 - 10' x 9.5' box culverts

Construction completed in Spring 2020.

Zemosa Acres Culvert Replacements

Chelwood

3 – 10’ x 9’ box culverts

Hanover

1 – 9’ x 8’ and 1 – 10’ x 8’ box culverts

Construction completed May 2019.

Wyoming Drive Culvert Replacements

 

Culvert #1

3 – 60” diameter reinforced concrete pipe (RCP)

Culvert #2

2 – 54” diameter reinforced concrete pipe (RCP)

Construction completed summer of 2018.

Shamrock Street Culvert Replacement

9’ x 6’ x 58’ box culvert

Construction completed in May 2017. 

Treasure Drive Culvert Replacement

20’ x 5’ arch culvert
Construction completed in Fall 2016.

 

Rubens Road Culvert Replacement

2 – 7’ x 6’ box culverts. 

Construction completed in Spring 2016.

Princess and Crowell Culvert Replacement

6’ x 7’ x 90.5’ box culvert.

Construction began in July 2015.  Completed in Fall 2015.

 

Zemosa Acres Culvert Replacements

Chadbourne Ave

 Before Construction
After Construction
       

 

Channing Ave

 Before Construction
  
After Construction

 

 Barnhardt Street - Culvert Replacement

 

 

During Construction

After

 Brown Street - Culvert Replacement

 

Utility Conflicts

Pipe Installation

Completed Project

McGee Park - Stream Restoration

 

Before

After